Project Timeplan

VeikoAunapuu edited this page Jul 3, 2024 · 13 revisions

2024

Updated timeline [2024-05-22]

gantt
    title Development timeline for Q1 and Q2 2024
    dateFormat  YYYY-MM-DD
    section Initial Phase
    Model retriever            :a1, 2024-03-13, 14d
    Validator                  :a2, 2024-03-13, 14d

    section Report Generation
    Report                     :b1, 2024-07-03, 2024-07-19

    section Task Management
    Task Generation            :c2, 2024-03-27, 2024-05-28
    Merge/Export               :c1, 2024-03-27, 2024-07-12
    

    section Replacement and Scaling
    Replace                    :d1, 2024-07-02, 2024-08-02
    Scaling                    :d2, 2024-07-02, 2024-08-02

    section Regional Modifications
    Regional Modifications     :e1, 2024-05-08, 2024-06-03

    section Kibana Dashboards
    Refactoring          :f1, 2024-08-01, 2024-08-31

    section Milestones
    RMM Merging possible       :milestone, 2024-05-28, 1d
    M6 RMM ACC Merge running      :milestone, 2024-06-03, 1d
    M7 CGM ACC Merge       :milestone, 2024-07-12, 1d
    M7.1 Report      :milestone, 2024-07-19, 1d
    M8 CGM ACC Scale + Replace     :milestone, 2024-08-02, 1d